Home of Our Own
Things You Might Like To Know:
We are one step closer to A Home of our Own! Board President Jan Austin signed the Earnest Money Contract on the building and surrounding grounds that we hope to purchase. We are now in the inspections phase of our journey.
As of February 22, all contracts have been signed and the inspection process has begun. We’ve done a walk-through of the property, and have received historical documents on prior inspections, flat, and floor plans from the seller.
We have a lot of work to do and we want as many of our Wildflower congregants to be involved in it as possible. If you want to get involved, please contact Paula Vaughan at or Jan Austin at  
|
Inspections Phase
February 11 – March 12
(30 Days)
|
|
|
What Happens?
|
· Architectural review
· Structural engineer
· Mechanical, electrical, plumbing engineer (with Austin Energy)
· EPA Phase I
· Title Land Survey
|
|
What will we learn?
|
· Whether there are any “show stoppers”
· What condition property and building are in
· Very rough estimate on upgrades, repairs and remodel
|
|
What will be decided?
|
Whether to proceed to next phase
|
|
Who is involved?
|
Building, Steering and Board decide; congregation informed
|
|
What is the cost?
|
$20,000
|